Designing and maintaining resilient standby power in a hospital demands careful coordination of clinical risk, electrical infrastructure and regulatory guidance. From load prioritisation and transfer times to fuel resilience and testing, every element must support the hospital’s operational requirements while satisfying the expectations of HTM 06-01.
For estates managers, Authorising Engineers and healthcare M&E consultants, the challenge is ensuring that hospital generators perform as intended when called upon, with the appropriate evidence to demonstrate system readiness.
At Rehlko, formerly Kohler Energy, we draw on extensive experience in healthcare power solutions to explore the key considerations for dependable standby generation and alignment with relevant compliance requirements.
Hospital electrical systems must support a wide range of services, each with different levels of risk and tolerance for disruption.
Life-safety loads and critical clinical services, including operating theatres and intensive care facilities, demand the highest levels of electrical protection. Operational systems such as ventilation, communications and building controls also play an important role in maintaining a functioning healthcare environment.
Effective standby power design therefore starts with understanding the consequences of supply interruption across the hospital, rather than treating all electrical loads as having the same priority. This means identifying which services require continuous power, which can tolerate a brief interruption and how essential functions will be restored safely.
The challenge for hospital estates teams is to balance these priorities with the practical demands of existing infrastructure, future capacity and system resilience.
A well-designed hospital generator installation must support the hospital’s wider electrical strategy, not simply meet its calculated power demand.
Health Technical Memorandum 06-01 (HTM 06-01) provides guidance on the design, installation, operation and maintenance of electrical infrastructure in healthcare premises. Applicable to both new and existing facilities, it establishes a framework for assessing electrical risks and designing resilient power distribution systems.
For hospital standby generation, this means considering more than generator capacity.
The system must be designed around the site’s essential electrical loads, the generator’s ability to accept sudden increases in demand, and the performance of the wider electrical infrastructure.
Generator configuration, control systems and commissioning procedures all play a part in demonstrating that the installation can perform as intended.
Importantly, HTM 06-01 is guidance rather than legislation. Its recommendations must be considered alongside applicable electrical standards and statutory obligations, with any proposed departures carefully assessed, justified and documented through the appropriate approval process.
Some HTM performance recommendations can also present practical challenges when specifying commercially available generating sets.
In our technical white paper, HTM 06-01: Commonly Used Generator Application Clarifications and Derogations, we explore these challenges, including generator load acceptance, equipment specifications and the implications of alternative design approaches.
HTM 06-01 uses clinical risk grades A–E and business risk grades I–IV to help healthcare organisations assess the consequences of electrical supply interruptions. These classifications inform which services require the highest levels of protection and how quickly power must be restored.
The guidance identifies different interruption-time bands, including 0–0.5 seconds, 0.5–15 seconds and 15 seconds to three hours. The appropriate response depends on the risks associated with each service, rather than a single restoration target applying throughout the hospital.
For equipment that cannot tolerate even a brief interruption, an uninterruptible power supply (UPS) provides immediate protection while standby generators start and accept their loads. This can include life-support equipment and essential equipment used during complex surgical procedures, where the clinical risk assessment identifies a need for uninterrupted power.
UPS and generators therefore perform complementary roles within the hospital’s resilience strategy.
At Royal Gwent Hospital, we supplied and commissioned four 650kVA generators, configured to synchronise and come online within 15 seconds. The project demonstrates how generator performance, control systems and transfer arrangements must work together to support essential hospital services.
A successful generator start doesn’t necessarily demonstrate that a hospital’s standby power system will perform reliably during a mains failure. Testing must also establish whether generators can accept the required electrical loads and whether automatic changeover arrangements operate correctly.
HTM 06-01 recommends weekly visual inspections and monthly generator testing using the building’s electrical load for at least one hour, preferably two. It also sets out recommendations for annual performance testing under load and testing automatic power-transfer switchgear.
Records of generator running hours and electrical performance during testing are also called for by HTM 06-01. These should sit alongside maintenance reports documenting identified defects and any remedial work undertaken, providing an auditable history of the system’s condition and performance.
For Authorising Engineers and hospital estates teams, this evidence helps establish whether the installation remains fit for purpose and whether outstanding issues could compromise electrical resilience.
The guidance also recognises the need to maintain electrical resilience during testing and servicing. In practice, this means coordinating planned exercises with hospital estates teams, assessing the risks associated with switching operations and arranging appropriate technical support to minimise disruption to clinical services.
Through our generator servicing and maintenance services, we support healthcare organisations in maintaining standby power equipment, identifying potential problems and planning corrective work before reliability is compromised.
Restoring essential electrical supplies is only the first stage of managing a prolonged mains failure. Hospital estates teams must also consider how standby generation can be sustained if the grid remains unavailable for an extended period.
HTM 06-01 recommends an on-site main fuel reserve sufficient for 200 hours of full-load operation for each standby generator. Where site constraints make this impractical, any proposed departure from the guidance needs to be assessed, justified and approved through the relevant governance arrangements.
Fuel resilience also depends on storage conditions, fuel quality and reliable replenishment arrangements. Contingency planning should account for delivery access, fuel consumption under operating conditions and the possibility of supply disruption during a wider emergency.
At Northampton General Hospital, our installation included extensive fuel-system works alongside new generating sets and associated infrastructure, demonstrating the importance of integrating fuel arrangements into the wider standby power design.
Servicing, repairing or upgrading standby power equipment in an operational hospital requires careful planning to avoid disrupting clinical services. Restricted access, limited working space and the need to maintain essential electrical supplies can all influence how and when work is undertaken.
Noise, vibration and infection-control considerations add further constraints, particularly where generator plant is located close to patient areas.
Maintenance activities may require controlled access routes, appropriate dust management and coordination with hospital infection prevention teams.
Planned shutdowns and switching operations must be assessed alongside clinical schedules, with contingency arrangements agreed before work begins. Where necessary, disruptive activities can be scheduled outside normal working hours to reduce their impact on patients and staff.
Our work with BMI Healthcare illustrates this approach. At Princess Margaret Hospital, we undertook switchgear and control upgrades over a Friday evening and Saturday, minimising disruption to hospital operations.
Effective coordination between specialist engineers, estates teams and clinical stakeholders helps ensure essential maintenance can proceed without unnecessarily compromising the hospital’s electrical resilience.
Ensuring reliable performance from hospital generators requires a coordinated approach to system design, HTM 06-01 guidance, commissioning and ongoing maintenance.
From the initial assessment of essential loads to routine testing and long-term fuel resilience, each element must contribute to a dependable electrical infrastructure.
With extensive experience supporting NHS and private healthcare facilities, we understand the challenges of designing, installing and maintaining standby generation in demanding clinical environments.
Whether you’re planning a new installation, upgrading existing equipment or reviewing your current arrangements, our team can help assess your requirements against the relevant healthcare guidance.