2MVA GENERATOR & E-POD INSTALLATION AT ROYAL CHESTERFIELD HOSPITAL

Power You Can Trust

2MVA DIESEL GENERATOR INSTALLATION AT ROYAL CHESTERFIELD HOSPITAL

INTRODUCTION

Chesterfield Royal Hospital NHS Foundation Trust provides general acute services for a population of over 400,000 to people living throughout North Derbyshire and beyond. To provide some measure of its capacity, Chesterfield has 15 wards and over 500 beds, in the year to the end of March 2023 it looked after over 32,000 people following planned operations, nearly 300,000 people were seen in outpatient clinics, treated more than 100,000 people in the A&E unit, all delivered by over 5,000 staff and volunteers.

PROJECT OVERVIEW

GENERATOR INSTALLATION

Installation of 2 x 1000kVA generating sets

EQUIPMENT REMOVAL

WB Power were responsible for the removal of the incumbent generator set and additional ancillary equipment

FUEL MANAGEMENT SOLUTION

Common 25,000 fuel tank installed in the inlet premium

PLANT ROOM INSTALLATION

The generating sets were installed in an existing plant room with limited space

SCOPE OF WORKS

WB Power Services were awarded the opportunity by the Foundation Trust to specify, design and install a standby power solution for the hospital, providing vital back-up power for the facility in case of a power failure. This case study looks to fully explore the innovative “one stop shop” packages that WB Power Services have been able to offer this client. From project design, providing optimised transformer and switchgear solutions, customised Kohler generating sets and associated control systems and WB’s Principal Contractor package which includes
all electrical installation and civil works.

This case study looks to fully explore the innovative “one stop shop” packages that WB Power Services have been able to offer this client. From project design, providing optimised transformer and switchgear solutions, customised Kohler generating sets and associated control systems and WB’s Principal Contractor package which includes all electrical installation and civil works.

The early design brief issued by the client sought for the replacement of two key substations, backed by standby generation complete with mains generator changeover, load bank connection point and output LV switchgear. Additionally, the generators were to be configured such that either generator could feed the other package and hence building. The package there included:-

  • Two package substation (one for each building)
  • Provision of N+1 standby generation
  • LV Switchgear
  • Electrical Installation
  • Development of control system philosophy and associated system software development
  • Civil works
  • Full design and project management of the site and associated works

GENERATING SET

Working closely with the client we identified that a 1000kVA 800kWe prime (PRP) rated generating set offered the optimum capacity and flexibility to meet their current and foreseeable needs. WB matched this requirement to our partner Kohler’s KD1100. When married to the appropriately rated Kohler KH03860T alternator the Kohler compact, fuel efficient, power dense and highly reliable 12-cylinder, 27 litre KD27V12-5DES engine can comfortably deliver the full power required. The sets were provided with a dual battery, dual battery charger and dual starter motor arrangement for enhance starting reliability and a 200-hour lube oil make up tank to ensure safe long term continuous running of the sets.

The two generating sets were housed in their own custommade acoustic containers rated to achieve a noise level of 65dBA @1m FFC (both sets running) and came complete with fire detection, fuel shut off valve and all internal lighting and ventilation. To minimise the footprint of the entire package the container housing the generator was designed to accommodate a penthouse style inlet and horizontal discharge arrangement. The dual roof mounted exhaust gas silencers were arranged for high level vertical discharge.

The key adaptation for these sets was the addition of a dual output circuit breaker package which was designed to facilitate the traditional load breaker and local LV load bank testing for each individual set. The generating sets were deployed in an N configuration with typically one generating set dedicated to feed its own building within the site.

GENERATOR CONTROL SYSTEM

The client expressed a preference for the use of a ComAp control system on both the generating sets and switchgear. The generating sets therefore utilise the ComAp Intelligen system configured for soft mains return. The ComAp control system also offers a comprehensive range of remote monitoring/status interface options which include RS485 and Modbus etc which are available via volt free connections, ethernet or fibre optic connections. In this application the generating sets are connected to the onsite BMS system.

FUEL SYSTEM

To reduce the overall footprint of each package it was decided to move away from the more conventional day tank, bulk tank and fuel distribution system. A “structural belly tank” solution was developed that would sit under each generating set. The tanks were sized at 5,000l (24 hours full load running) usable capacity to meet the client’s operational requirements can came complete with a fuel fill point and fuel polishing system.

TRANSFORMER, SWITCHGEAR CONTAINERS AND CONTROL SYSTEM

The total package provided for the replacement of two substation each of which feeds a building within the hospital campus. As with the generator containers the two substation/ switchgear containers were also identical. Each of the switchgear containers is fitted with:

  • 1 x Schneider Electric SN6-S1-21 630A non-extensible switch disconnector
  • 1 x 1000kVA ANAN 11kV/417V (no load) aluminium wound energy efficient cast resin Transformer with, temperature relay & PT100 sensors
  • 1 x Schneider Electric MTZ1 06 HA 630A 3P neutral earth device
  • 1 x tripping batteries
  • All key motorised circuit breakers managed by a ComAp controllers
  • Provision of ComAp schematic display panels and HMIs located at key points throughout the system
  • External link box for connection of temporary generating set
  • 1 x 1600A rated form 4 type 6 distribution board with:
    • Mains / Generator change over
    • Load bank connection point
    • A mid busbar section switch splitting the outgoing distribution ways into essential and non-essential elements
    • An end of line interlocked bus section switch allowing for interconnection between boards in both panels designed to permit either generator to feed the essential load of the other board / building
    • Connection for power factor correction equipment
    • Power monitoring on all incoming and out going ways

The Transformer section is a naturally ventilated IP2X sheet steel enclosure complete with double access doors and fitted with Castell lock to prevent unauthorised access.

CONTAINERS

All containers were fitted with internal and external lighting (with some emergency fittings), heating and ventilation (as required) to ensure all operations requirements of the installed equipment were covered. Additional safeguards were also put in place with the use of internal bulkheads assess to which were controlled by key interlock systems, fire alarm panel, smoke detection and associated warning lights and beacons. The generator and switchgear containers were levelled to ensure that roof heights match. This allowed for duct work and cable access from below to the two switchgear containers. Busbar flange connection to manage the busbar interconnections between the generator and switchgear enclosures.

CIVIL WORKS

The civil works associated with the project formed a significant part of the overall works and included elements such as:

  • Excavations to max depth of 1.5m to level the site plus material disposal and compacting excavated area
  • Earth works supports to 4m depth
  • Back filling and levelling for structural bases
  • Construction and forming of service ducting / trenching
  • Provision and installation of ducting and piping for surface water drainage
  • Excavation and installation of land and channel drains including brick and concrete surrounds for manholes etc with connection to existing drainage system

 

MECHANICAL INSTALLATION

The mechanical works also formed a major part of the works and included such elements as:-

  • Site survey and builders work installation and coordination drawings
  • Prestart investigations and tests
  • Identification and removal of redundant services
  • Management of domestic water and gas supplies

ELECTRICAL INSTALLATION

As well as providing a full suite of electrical services within each of the containers WB undertook, as part of the installation package, the provision of all of the power, control and interface connections between the containers. Power connections being provided in busbar. In addition to provision of the inter container connectivity WB undertook the provision of some of the following:-

  • All prestart inspections and drawing validations
  • The making safe, disconnection and marking up of redundant electrical equipment to permit stripping out
  • The stripping out and removal from site all redundant equipment
  • The provision of High Voltage works
  • The provision of undertaking the whole G99 DNO Connection process and implementation of protection settings including all testing and witnessing
  • The provision of a new below ground earthing installation and associated earth bonding
  • The provision of new sub mains distribution installation

TESTING & COMMISSIONING

All four containers underwent a series of factory acceptance tests prior to being delivered to site. Providing modular packaged solutions of this type means that much of the testing can be completed before delivery cutting down site installation and commissioning time.

DESIGN & PROJECT MANAGEMENT

Having received the initial design brief from the client WB worked closely with its partners and the Trust to provide a fully developed design before proceeding with production. Close liaison with the Estates team at all stages ensured that the packaged solution met with the brief and operational requirements of the hospital. One method WB adopt in this type of project is to ensure that its project managers are involved at an early stage in the development of any design. This works to ensure that we fully utilise their wealth of practical onsite knowledge the PM has such that they both contribute to the design and have a clear understanding of the project once itgoes to site for installation.

WB were awarded the project as Principal Contractor and as such took on all responsibilities required to fulfil that role which include, taking full responsibilities for control and management of the site area, Health and Safety, staff inductions, welfare facilities, site security and all temporary service etc. A full site management team was put in place which included contract manager, project manager, QS, HSEQ inspections etc