WAKEFIELD DATA CENTRE
The solution included the provision of four 1100kVA generators with the capacity to run for 72 hours on full load, 2 x 3MVA HV transformers, local HV switchgear and HV infrastructure with 5,000A rated switchboard inclusive of automatic changeovers, UPS input and output boards and site distribution.
The whole package has been designed by our Project team and includes the latest state-of-the-art PLC controls and power management systems. Furthermore, the panels were manufactured in the client’s company colours, to keep in-line with their corporate branding.