2.6MVA Diesel Generator Installation at Royal Gwent Hospital

PROJECT OVERVIEW

GENERATOR INSTALLATION

Four new 650kVA prime rated Kohler-SDMO generators installed in containerised units 

BESPOKE ACOUSTIC ENCLOSURES

The generator was designed in bespoke containers rated to achieve a noise level of 70dBA @ 1m 

FUEL MANAGEMENT SOLUTION

The new generator set was designed to link into an existing fuel distribution system connected to a bulk tank

THE CLIENT

The Royal Gwent Hospital is a district general hospital in the city of Newport. It is managed by the Aneurin Bevan University Health Board. WB Power Services were appointed to supply, install, test and commission four new 650kVA Kohler / SDMO generators for Royal Gwent Hospital, supplying back-up power to existing and new facilities within the hospital. 

 

OVERVIEW

WB Power Services were appointed to scope, supply, install and commission four new generators for Royal Gwent Hospital. Included in the package was also fuel distribution, switchgear upgrades, control system and control cable installations.

PROJECT BRIEF

WB Power Services have supplied, installed, tested and commissioned four new 650kVA Kohler-SDMO generators for Royal Gwent Hospital, supplying back-up power to existing and new facilities within the hospital. The generators are housed in close fit factory built enclosures that were engineered to fit within a newly created but very compact compound area.

SOLUTION & RESULT

The generating sets were supplied with the advanced Kohler / SDMO APM802 control system which ensured that all of the sets were synchronised and online well within the 15 second requirements of HTM 06.

The installation package provided by WB Power Services included a difficult off load and positioning process, a new fuel distribution system connected to the existing bulk tank as well as upgrades to the switchgear and installation of all necessary interconnecting power and control cables.

The 4 x 650kVA prime rated Kohler- SDMO generating sets, which use the highly  regarded Volvo engines, underwent rigorous load testing at our headquarters prior to delivery to site.