WB Power Services project managed the delivery, installation and commissioning of two 3000kVA 11kV prime rated generating sets. Each housed in bespoke sound reduced enclosures, manufactured to the consultants exacting standards, with the total package fully meeting the requirement of HTM-06.
Both enclosures were designed to meet a sound level not exceeding 65dBA @ 1m. The generators were linked with an 8 hour capacity local day tank adjacent to the container with the fuel supply connected directly to the hospital’s bulk fuel system.
The advanced Kohler / SDMO AMP802 generator control system was designed to fully integrate with the hospital’s building management system (BMS) to provide a comprehensive generator monitoring and duel redundant control of the HV distribution.